STARC’s modular reusable temporary containment provides significant cost savings over time versus building drywall containment and rapid payback on the investment, usually after 3-5 uses. Because it’s extremely durable,  these temporary construction walls can be used on hundreds of jobs year after year.

Drywall Installation

  • One time use only
  • Noisy and disruptive
  • Creates harmful dust
  • Environmentally unfriendly

STARC Installation

  • Pays for itself in 3-5 uses
  • No disruption to patients and staff
  • Exceeds ICRA Class IV requirements
  • Durable and reusable

Sample Project Plan – 6 Phases Total

This is a sample renovation plan for a healthcare facility requiring 6 phases and 1,282 linear feet of containment.

 

Positive ROI Achieved After Just One Job With 6 Phases

This chart compares the cost of owning STARC temporary containment versus building drywall containment. Your investment in STARC’s reusable temporary containment is paid for after phase 5 virtually eliminating your future containment costs and the walls can be used on hundreds of jobs.

Project Phase Linear Feet / Phase Drywall Costs (@$100/lf) Cumulative Drywall Costs by Phase STARC Costs (@ $375/lf) Comments
Phase 1B 224 $22,400 $84,000 The initial phase 224 linear feet will satisfy all but one phase of the job
Phase 2 202 $20,200 $42,600 $0
Phase 3 270 $27,000 $69,600 $17,250 Phase 3 requires the most linear feet and requires an additional 46’ of STARC containment to satisfy
Phase 4 199 $19,900 $89,500 $0
Phase 5 172 $17,200 $106,700 $0 Break-even achieved after 5 uses
Phase 6 215 $21,500 $128,200 $0
Total 1,282 $128,200 $101,250